CIP#85 - Water Main Replacement - Community Drive, Walnut Street and Sanders Street
Early next week, the contractor will finish installing the water services on Sanders Street. Mid-week, they will begin to install the temporary and new water mains on Walnut Street. Local traffic disruptions are expected.

October 13, 2017 Update:
The contractor will be installing the new sanitary sewer main on Sanders Street. Residential services are not anticipated to be disrupted. Traffic will be restricted to local use only.

October 6, 2017 Update:
Next week, the contractor will be installing temporary water and new sanitary sewer on Sanders Street. Local traffic only.

On Wednesday, the contractor will be installing two water valves on Portsmouth Street,
in the vicinity of the trail head parking lot. Residents between #1 and #55 Portsmouth Street
will be without water from 9:00 AM to 6:00 PM. Paving of this section of Portsmouth Street will occur on Friday. The road will be closed to through traffic during this time.

September 29, 2017 Update:
Next week, the contractor will be grading Community Drive in preparation for paving on Friday. On Thursday, temporary water will be set up on Sanders Street and the street will be reclaimed. On Friday, the contractor will begin to replace the water main on Sanders Street. Traffic delays
are expected.

September 22, 2017 Update:
The contractor will be installing new sanitary sewer manholes and services on Community Drive next week. If time allows, the road will be graded and prepped for paving the following week.

September 15, 2017 Update:
Next week, the contractor will be installing new water services along Community Drive. Local traffic delays are expected.

September 8, 2017 Update:
SUR continues to connect water and sewer service lines to homes on Community Drive. Work area will be restricted to local traffic only.

September 1, 2017 Update:
The contractor will continue to connect services on Community Drive next week. With school back in session, residents are asked to use High Street to access the school during AM/PM drop off and pick up hours. Allow extra time to arrive at your destination. Traffic delays are expected.

August 25, 2017 Update:
The contractor has finished installing the new water main on Community Drive. Next week, they will continue testing the new main and then begin installing new service connections to the properties. They will also focus on connecting the hydrants to the new main. Traffic will be restricted to local traffic only.

August 18, 2017 Update:
The contractor will continue to install the new main on Community Drive from 40 Community Drive to Shaw Street. This will complete the main installation. The new main on Community, between Allen and Dolphin, will be pressure tested and chlorinated. The end of the week work will focus on connecting the hydrants to the new main. Traffic is restricted to local traffic only.

August 11, 2017 Update:
The contractor will continue to lay water main on Community Drive, from Dolphin Street north to #44 Community Drive. Local traffic only.

August 4, 2017 Update:
The contractor will be installing the new water main on Community Drive beginning at Allen Street and ending at Rolfe Park. All residents have been hooked up to the temporary water main. Local traffic detours may be implemented.

July 28, 2017 Update:
On Monday of next week, the City's contractor will be removing road materials between Allen and Dolphin Street. On Tuesday, the houses will be switched over to the temporary water main. No water disruptions are anticipated. The new water main installation will begin at the end of the week. Traffic disruptions are anticipated.

July 21, 2017 Update:
Next week, SUR Construction will be installing two new water valves on Portsmouth Street. This work is in advance of the Portsmouth Street Culvert Replacement Project. Residents will be without water during this time. Traffic will be reduced to alternating one lane traffic.

July 14, 2017 Update:

The contractor, SUR West Construction, Inc. will mobilize their equipment and materials next week. They will be staging on property owned by Merrimack Valley School District off of Beede Drive. Work will begin on Community Drive(at the Allen Street end) with setting up the temporary water at the end of the week. There will be minimal disruption to the residents.